Skip to content
West Genesee Street Mill & Pave Project

West Genesee Street Mill & Pave Project

  • Home
  • Project Information
  • Project Plans
  • Photo Gallery
  • Questions/Comments

Photo Gallery

Share this:

  • Twitter
  • Facebook

Like this:

Like Loading...

Project Location

View Preliminary Project Plans

Project Objectives

  • Restore pavement to good condition using cost effective pavement treatments to extend the pavement service life.
  • Correct safety deficiencies using cost effective crash reduction measures such that crash reduction benefits equal or exceed project costs attributable to safety work
  • Provide ADA-compliant pedestrian infrastructure throughout the project corridor
  • Provide all new pavement markings throughout the corridor which are compliant with latest standards.

Anticipated Project Schedule:

Project Design Approval:    January 2021

Project Construction Begin:     June 2022

Project Construction Complete: November 2022